6-05-01 Walls are Painted and Casework ready for installation in the Teacher's Workroom.
6-05-01 Casework to be installed for the Student Services Reception Counter.
6-05-01 Finish Colors and Textures coming to life at the Administration Building.
6-05-01 Concrete Planter Walls are installed at Building E Courtyard.
6-05-01 Finish Painting underway of Canopy at Classroom Building E.
6-05-01 Radius Steel Trusses are installed at Multi Purpose Building Roof.
6-05-01 Radius Steel Canopy Trusses installed at Main Entry of Multi-Purpose Building.
6-05-01 Finish Plumbing Fixtures are installed at Administration Building Restroom.
5-15-01 Welders installing Open Web Steel Canopy Trusses.
5-15-01 Overview of Madison Campus with Classroom Building E in Foreground.
5-15-01 Overview of Madison Campus with Classroom Bldg F in Foreground.
5-15-01 Main Entry of Multi Purpose Building.
5-15-01 North Elevation of Multi Purpose Building and Kitchen.
5-15-01 Edge Concrete crews beging layout and foundations for Building E Courtyard.
5-15-01 Exterior Painting of Administration Building.
JP Witherow crews installing roofing at Administration Building.
5-15-01 North Elevation of Phys. Ed. Building.
Overview of Madison Campus, looking South.
Standard Drywall's plastering crews applying plaster to the Administration Building.
Opening in masonry walls create main entry to Multi-Purpose Building
Overview of Madison Campus with Classroom Building E in Foreground, Administration, and Multi-Purpose in Background.
Drywall being installed at Lobby of Administration Building.
Structural Steel and Wood Framing of Library Building is ongoing.
EDGE Framing crews working on buildings A & E.
Building A Rough Framing is nearly complete.
EDGE Framing crews completing Building A rough framing.
Progress photo taken 11-28-00 looking toward the southside of project.
Progress Photo September 2000.
Building B masonry ready for first lift of grout.
Building C structural steel erection on going.
McMahon Steel crews erecting steel on building C.
Build D slab on grade is ready for concrete.
Progress photo Madison middle School December 15, 2000.
Building D ready for slab on grade.
EDGE Concrete crews working on Bldg E relo foundations.
Building E wall framing complete and ready for roof framing.
EDGE Concrete crews excavating foundations for building F.
EDGE crews framing walls in building G.
Building E, A and B in the background. January 16, 2001.
Madison Middle School progress photo January 16, 2001.